MANILA, Philippines — The Metropolitan Manila Development Authority (MMDA) has proposed the construction of rainwater impounding facilities inside Camp Aguinaldo to ease recurring flooding along EDSA, with the proposed design released on Wednesday.
The plan calls for detention ponds that will temporarily store excess rainwater during downpours and gradually release it into the EDSA drainage system leading to Makiling Creek.
According to the proposal, the project will be implemented in three phases covering 182 hectares: a golf course near Gate 2, another near Gates 3 and 4, and an open space near Gate 6.

For the first phase near Gate 2, the detention pond has a 361-meter perimeter, a 4,650-square-meter area, an 8-meter depth, and a 37,200-cubic-meter capacity, designed for a 25-year return period (15.6 mm/hr over 24 hours) and exceeding the needed 36,945 cubic meters.
MMDA’s schematic shows that under normal weather, water bypasses the pond and traverses the lagoon to EDSA; during heavy rains, floodgates divert flows into the pond; after rains, pumps discharge stored water slowly to EDSA toward Makiling Creek.
MMDA unveils plan to build rainwater impounding facilities in Camp Aguinaldo, This news data comes from:http://ghboebo.jyxingfa.com
The scope of work covers the impounding area, an operations and power house, drainage and electromechanical works, and landscaping and golf course restoration, with a treatment facility under consideration.
Officials said operations and maintenance arrangements and a memorandum of agreement were being discussed..
- Comelec to open nearly two-year overseas voter registration for 2028 elections
- Pope declares 'God's influencer' first millennial saint
- 'Large shark' kills man off Sydney beach
- COA launches sweeping audit of flood control projects
- Israel army urges Gaza City residents to leave
- Russian drone, missile attack kills 14, injured 48 in Kyiv
- Social media erupts: Politicians' children face backlash for flaunting wealth
- DPWH Secretary Dizon vows to slash 'staggering' P268B flood control budget
- HEADLINES: 15 drug war victims cleared to join Duterte's ICC case | Sept. 7, 2025
- DILG suspends classes, gov’t work in 17 areas